Concrete Pour Planner

Offline pour-day tool for concrete contractors — volume, evaporation risk, truck pacing, weather rules.

1 · Pour setup

2 · Evaporation-rate risk (ACI 308)

Method note — ACI 308R evaporation equation (Menzel)
E = (Tc^2.5 − r × Ta^2.5) × (V + 4) × 10⁻⁶

E = evaporation rate, lb/ft²/h. Tc = concrete temperature (°F). Ta = air temperature (°F). r = relative humidity as a decimal fraction (0–1). V = wind velocity (mph). Basis of the ACI 308R nomograph for estimating surface evaporation; negative raw values (humid air over cooler concrete) are reported as 0 — conditions then favor condensation, not drying.

Risk tiers: ≥ 0.20 lb/ft²/h — HIGH (ACI 308R recommends precautions against plastic-shrinkage cracking above this rate); 0.10–0.20 — MODERATE (have countermeasures ready); < 0.10 — LOW (standard curing). Planning aid — not a substitute for engineer judgment.

3 · Truck interval & pacing

4 · Hot / cold-weather placement checklist

Rules paraphrased from ACI 305R (hot-weather concreting) and ACI 306R (cold-weather concreting) guidance. Verify against the current standard and your project specification — planning aid only.

Pour sheet

One-page summary for the foreman — print and take to site.

Data — backup, restore, samples

Everything is stored only in this browser (localStorage). No account, no network, no cloud.